India Bullet Train 2027 : India's first bullet train project has received a major update, with Railway Minister Ashwini Vaishnaw stating that high-speed rail services are targeted to begin in the final quarter of 2027. The initial service is expected to operate between Surat and Vapi. The entire corridor to Mumbai will then be opened in phases. Construction is progressing rapidly, with several major sections of the project already completed.
456 Km of Pillar Construction Completed
According to the Railway Minister, 456 kilometres of pillars had been completed by September, while 371 kilometres of viaduct construction had been finished. Around six lakh noise barriers have been installed along nearly 299 kilometres of the corridor. In addition, 9,300 overhead electrification (OHE) masts have been installed across 206 kilometres of viaduct. These structures are essential for preparing the bullet train track infrastructure and electrical systems.
Excavation Completed for Four Mountain Tunnels
Excavation work on four mountain tunnels under the project has reportedly been completed. In Maharashtra, approximately five kilometres of a nearly 21-kilometre tunnel have been excavated using mountain tunnelling techniques. Civil construction work at eight stations has also been completed, with architectural finishing now underway. Construction of train depots in Sabarmati, Surat and Thane is progressing rapidly as well.
Seven-Kilometre Tunnel to Run Under Sea
The Maharashtra section of the Mumbai-Ahmedabad High-Speed Rail Corridor will pass through a 21-kilometre tunnel, including a roughly seven-kilometre section beneath the sea across Thane Creek. Two tunnel boring machines (TBMs) were deployed in July 2026 from Vikhroli and Savli for the excavation work. They are reportedly among the largest TBMs used in India, with each machine measuring 96 metres in length and weighing more than 3,000 tonnes.
Indigenous Bullet Trains to Be Developed
India is also working on developing its own high-speed trainsets. ICF and BEML are jointly manufacturing the B28 trainset, designed to operate at speeds of 280 kmph. Its first body frame has been completed, and structural testing is underway. Track trials are expected by mid-2027. Following this, India plans to develop the B35 train, designed for a speed of 350 kmph. The initiative could strengthen India's indigenous high-speed rail technology capabilities in the coming years.